Preparation Phase 10
Phase 10 Completed Projects
Date Started December 26,2018
Target Completion Date March 10,2019
Owner : Nepheteri Villamena
Project Location : Blk 5, Lot 6 Francisco St, Pasong Buaya 2, Imus City, Cavite


Before
After

Demolition of the old house
Removing debris from the old house
Digging the foundation of the house

Prepared foundation of the house
Rectangular steel frame has been installed
Foreman Joe assign at the pouring of concrete to make sure the mixture of the cement,sand and gravel are meet the requirements.

Portable concrete mixers are used giving the workers ample time to use the concrete before it hardens.

The key to achieving a strong, durable concrete rests in the careful proportioning and mixing of the ingredients.
Worker is checking the elevation of the base of the flooring.

Preparing the grade beam of the house
Foreman checking all the measurements of the layout before starting to work
Construction of wall surface and window


Finishing of wall surface garage area

Installation of support beam of the house
Installation of Roof Framing

Roof has been installed

Finishing of the interior of the house.

Installation of pipeline has been completed

Installation of door jamb (back area)

Installation of ceiling frame has been completed
Installation of electrical wiring has been completed


Installation of tiles at living room area

Workers started to demolish the old gate (front area)

Workers preparing the installation of the house railing ( front area)

Workers finishing the concrete slab infront of the house

Engr. Ronald Bravo verifying the completion of the house

Preparing the ceiling board

Installation of ceiling board has been completed

Preparing the final mixture color for the bar cabinet

Preparing the kitchen cabinet for painting
( Layer coating to smoothen the surface and for protection against moisture )

Installation of new cabinet at 2nd bedroom area
Workers finishing the installation of tiles at wall surface (living room area)


Preparing the installation of tiles
(Master Bedroom Area)

Circuit breaker has been installed

Preparing the installation of tiles
(front area)

Tiles installation at front gate area

Garage gate has been installed
Worker assigned has verifying the gate arm if properly attached.








Phase 10 Completed Projects
Finishing Operation
Target Completion Date March 10,2019

Completion of wall tiles at living room area.
Completion of bar at living room area.

Finishing of common comfort room

Finishing of living room area
Cove light ceiling drop has been completed

Door installation at mid section has been installed


Lighting at mid section has been completed

Installation of enclosing steel bar, air conditioned and light bulb has been completed at the mid section of the house.
( Air ventilation spacer area )

Installation of cabinet at 2nd bedroom area has been completed

Lighting at 2nd bedroom has been completed

Finishing of cabinet at master bedroom area.
Finishing of ceiling drop cove lighting at master bedroom area.


Completion of comfort room at master bedroom area

Door panel has been installed

Finishing of main kitchen area

Finishing of dirty kitchen area has been completed

Finishing of support beam and window
Completed Finishing
Finalizing the front gate area of the house


Installation of tiles at front gate area

Front view of the house
​
( garage gate, front gate lights, doorbell are all working properly )