Preparation Phase 10

 Phase 10 Completed Projects

 Date Started December 26,2018 

 Target Completion Date March 10,2019 

 Owner : Nepheteri Villamena 

 Project Location : Blk 5, Lot 6 Francisco St, Pasong Buaya 2, Imus City, Cavite 

3.0 Phase 10 Before.jpg
3.1 Phase 10 After.jpg
Before
After
1 demolition.jpg
Demolition of the old house
Removing debris from the old house
Digging the foundation of the house
2.1 preparing the house foundation.jpg
Prepared foundation of the house
Rectangular steel frame has been installed

Foreman Joe assign at the pouring of concrete to make sure the mixture of the cement,sand and gravel are meet the requirements.

4 pouring of cement in the foundation.jp

Portable concrete mixers are used giving the workers ample time to use the concrete before it hardens.

5 mixing the cement.jpg

The key to achieving a strong, durable concrete rests in the careful proportioning and mixing of the ingredients.

Worker is checking the elevation of the base of the flooring.

6.1 house column support has been instal

Preparing the grade beam of the house

Foreman checking all the measurements of the layout before starting to work

Construction of wall surface and window

7.1 Layout for wall surface and garage a
7.2 finishing of wall surface at garage

Finishing of wall surface garage area

7.3 support beam has been installed.jpg

Installation of support beam of the house

Installation of Roof Framing

7.3.2 roof has been installed.jpg

Roof has been installed

8 finishing of the interior of the house

Finishing of the interior of the house.

8.1 installation of pipeline.jpg

Installation of pipeline has been completed

8.2 installation of door jamb has been c

Installation of door jamb (back area)

8.3 installation of ceiling frame has be

Installation of ceiling frame has been completed

Installation of electrical wiring has been completed

8.4 installation of electrical wiring ha
9 installation of tiles at living room.j

Installation of tiles at living room area

10 workers started to demolish at front

Workers started to demolish the old gate (front area)

10.1 new design and layout of the gate .

Workers preparing the installation of the house railing ( front area)

10.2 workers finishing the slab infront

Workers finishing the concrete slab infront of the house

10.3 engr Ronald verifying the completio

Engr. Ronald Bravo verifying the completion of the house

10.4 installation of ceiling frame.jpg

Preparing the ceiling board

10.5 drop down celing cove.jpg

Installation of ceiling board has been completed

10.5.1 preparing the final mixture of pa

Preparing the final mixture color for the bar cabinet

10.5.2 preparing the kitchen cabinet.jpg

Preparing the kitchen cabinet for painting

( Layer coating to smoothen the surface and for protection against moisture )

10.5.3 preparing the installation of cab

Installation of new cabinet at 2nd bedroom area

Workers finishing the installation of tiles at wall surface (living room area)

10.6 finishing of installation of tiles
10.6.1 installation of tiles masterbedro

Preparing the installation of tiles
(Master Bedroom Area)

10.6.3 circuit breaker.jpg

Circuit breaker has been installed

10.6.4 installation of tiles front gate

Preparing the installation of tiles 
(front  area)

12.1 installation of front gate tiles.jp

Tiles installation at front gate area

12.2 workers verifying the attachment of

Garage gate has been installed

Worker assigned has verifying the gate arm if properly attached.

1.1removing debris.jpg
2.0 preparing the house foundation.jpg
3 rectangular steel frame has been insta
4.1 mixer machine has been used.jpg
6 foreman checking the base of the floor
7 head foreman checking all the measurem
7.3.1 installation of roof framing.jpg
finalizing the front gate area.jpg

Phase 10 Completed Projects
Finishing Operation

Target Completion Date March 10,2019

10.10 wall tiles has been completed.jpg

Completion of wall tiles at living room area.

Completion of bar at living room area.

10.11.1 comfort room.jpg

Finishing of common comfort room

10.11 lobby section has been completed.j

Finishing of living room area

Cove light ceiling drop has been completed

11.0.1 door installation at spacer area.

Door installation at mid section has been installed

10.12 cove light ceiling drop at living
11.1 lighting midsection.jpg

Lighting at mid section has been completed

11.0.0 installation of enclosing steel b

Installation of enclosing steel bar, air conditioned and light bulb has been completed at the mid section of the house.

( Air ventilation spacer area )

11.1.2 finishing of cabinet at 2nd bedro

Installation of cabinet at 2nd bedroom area has been completed

11.3 installation of lighting at 2nd bed

Lighting at 2nd bedroom has been completed

11.5 finishing of cabinet master bedroom

Finishing of cabinet at master bedroom area.

Finishing of ceiling drop cove lighting at master bedroom area.

11.4 cove light ceiling drop at master b
11.6 finishing of comfort room masterbed

Completion of comfort room at master bedroom area

11.1.1 door installation back area.jpg

Door panel has been installed

11.7 finishing of kitchen.jpg

Finishing of main kitchen area

11.8 finishing of dirty kitchen.jpg

Finishing of dirty kitchen area has been completed

12.0 furnishing of support beam front ar

Finishing of support beam and window

Completed Finishing

Finalizing the front gate area of the house

11.9 bar.jpg
installation of tiles at front gate area

Installation of tiles at front gate area

13.0 front gate of the house.jpg

Front view of the house

​

( garage gate, front gate lights, doorbell are all working properly )